PCR Number | VNP 23-002 |
---|---|
Date | 2023-02-16 |
Initiator | Sudipta Sarkar, Carol Davidson, Huilin Gao |
Abstract | PGE687 2.0.1, PGE688 2.0.1, PGE698 2.0.1 Initial version of the Global Reservoir suite of PGEs, PGE687, PGE688, and PGE698, developed at SCF in Texas A&M University, followed by suitable loader module (LM) and production rule updates and additions by LandSIPS STIG to complete the transition to a LandSIPS PGE. Specific Algorithm Change/Improvements, following the initial delivery:
|
Problem Statement | Introduction of the JPSS1 and SNPP VIIRS version of the Global Water Reservoir products, as part of the VIIRS Collection 2 (C2) and onwards. Specifically, this suite will include the SNPP versions of CMG VNP28C2/C3 products and the JPSS1 versions the CMG VJ128C2/C3 products. |
Description of Change | Initial version of the Global Reservoir suite of PGEs, PGE687, PGE688, and PGE698, developed at SCF in Texas A&M University, followed by suitable loader module (LM) and production rule updates and additions by LandSIPS STIG to complete the transition to a LandSIPS PGE. Specific Algorithm Change/Improvements, following the initial delivery:
|
Products Affected | VNP28C2, VNP28C3, VJ128C2, and VJ128C3 |
Software Affected | PGE687 2.0.1, PGE688 2.0.1, PGE698 2.0.1 |
Processing String to Receive the Change | S-NPP Forward Processing. S-NPP Reprocessing. J1 Forward Processing. J1 Reprocessing. |
Downstream Product Effects | SNPP VIIRS Land products, including VNP28C2/C3 and VJ128C2/C3 |
Data Granules to be Used for Science Testing | Several science tests have been carried out, including one final one in AS 4007, to assess the performance of these products. All results have been duly reviewed and confirmed by the science team and LDOPE, before final approval. |
Justification | The introduction of the SNPP and JPSS1 VIIRS Global Reservoir products will ensure the continuity with the MODIS heritage products and will provide critical datasets that are requested by the user and the modeling community. |
Effective Date for Implementation of Change | PGEs noted in this document are expected to go into production, as part of the C2 reprocessing the week of February 13, 2023 for SNPP and JPSS1. |
Status | Major algorithm development completed. Sadashiva Devadiga approved 02/22/2023. Sudipta Sarkar approved 02/17/2023. |