MODAPS PCR 23-008

PCR Number 23-008
Date 2023-12-18
Initiator Sanjeeb Bhoi
Abstract PGE104 1.0.10
Updated run_abi_17_v1.bash and PGE104_G17_LoaderModule.pl to use the path /tis/modaps/goesr/plt10/GOES-17-ABI-L1B-FULLD/ for dates 2018-001 to 2019-042 i.e post-launch test data.
Problem Statement Needed to update the GOES ABI G16/G17 version of PGE104 to use the post-launch uncalibrated version of GOES-West (G17) Advanced Baseline Imager (ABI) instrument data, for processing the first 42 days of 2019, as per science team request.
Description of Change Specific Algorithm Change/Improvements for this DT Package as compared to 1.0.5 is:
  1. Updated perl script and PGE104_G17_LoaderModule.pl and run_abi_17_v1.bash to use the path /tis/modaps/goesr/plt10/GOES-17-ABI-L1B-FULLD/ for dates 2018-001 to 2019-042 ie post-launch test data.
  2. Based on version 1.0.5, we will keep using DFPITI3NXASM as ANC inputs.
Products Affected C1 L2 GEO products, XAERDT_L2_ABI_G16 and XAERDT_L2_ABI_G17.
Software Affected PGE104 1.0.10
Processing String to Receive the Change ABI-G16 Forward Processing. ABI-G16 Reprocessing. ABI-G17 Forward Processing. ABI-G17 Reprocessing.
Downstream Product Effects None.
Data Granules to be Used for Science Testing A series of science tests have been carried out to assess and fully confirm all production rule and science changes in AS5019. The outputs from this test were fully assessed and approved by LDOPE and the science team.
Justification The will allow the Collection 1 (C1) MEaSUREs GEO G17 products to be fully complete for the data year 2019, including the missing first 42 days of the year.
Effective Date for Implementation of Change This revised version was used to complete the ABI G17 processing for the remaining days of 2019, as of 12/05/2023, with due confirmation from the science team and LDOPE.
Status Sudipta Sarkar implemented on 12/18/2023.